Previous  Next          Contents  Index  Navigation  Glossary  Library

Audit Reporting for Expenditure Adjustments

Oracle Projects provides an audit trail of all adjustments performed on an expenditure item. The audit trail records the following information about the adjustment for an item:

Oracle Projects also records the audit trail to the original item for transfers, splits, and corrections to approved items. With this audit trail, you can identify where an item was transferred or where an item was transferred from.

You can review the expenditure adjustment audit information for a project in the AUD:Project Expenditure Adjustment Activity report. You can review the transfer activity for a project using the MGT: Transfer Activity report.

See Also

Project Expenditure Adjustment Activity

Transfer Activity Report


         Previous  Next          Contents  Index  Navigation  Glossary  Library