Revising an Original Budget
The first time you baseline a budget, that budget becomes the Original Budget. The Project Status window displays information in the Original Budget and the Current Budget.
You may want to modify the Original Budget to correct data entry errors or scope changes which you want to include in the original budget amounts.
Oracle Projects uses the latest revised original budget as the Original Budget in reporting.
To revise an original budget:
1. Choose the New Original box in the Budgets window.
2. In the Budget Lines window, enter the revised budget amounts for the draft.
4. Choose Baseline. Oracle Projects creates a new version which is identified as the new Current Budget and the new Original Budget.