Interfacing Assets to Oracle Assets

You can interface asset costs from Oracle Projects to Oracle Assets whenever you are ready and as many times during an accounting period as you wish.

Submitting Processes

When you are ready to place your CIP assets in service, you can interface the asset costs to Oracle Assets. You interface asset cost lines by running the Oracle Projects process PRC: Interface Assets. You can run this process whenever you are ready and as many times during an accounting period as you want. You can run the process for a single project or for a range of projects. You can choose to interface costs for assets that are placed in service as of a date you specify in the processing parameters.

Prerequisites