The project type determines which revenue distribution rule appears as the default value for this field, and which other revenue distribution rules you can choose from. Oracle Projects predefines the following revenue distribution rules:
Cost/Cost | Accrue revenue and bill using the ratio of actual cost to budgeted cost (percent spent). |
Cost/Event | Accrue revenue using the ratio of actual cost to budgeted cost (percent spent), and bill based on events. |
Cost/Work | Accrue revenue using the ratio of actual cost to budgeted cost (percent spent), and bill as work occurs. |
Event/Event | Accrue revenue and bill based on events. |
Event/Work | Accrue revenue based on events, and bill as work occurs. |
Work/Event | Accrue revenue as work occurs, and bill based on events. |
Work/Work | Accrue revenue and bill as work occurs. |
Note: If you want to accrue revenue or generate invoices based on percent complete, you must use the Event/Event, Event/Work, or Work/Event revenue distribution rule. See: Percent Complete Revenue Accrual and Invoice Generation.
Next Billing Date displays the next billing date on which the project is eligible for billing. The Next Billing Date is updated each time draft invoices for the project are released, cancelled, or deleted.
Enter a format for this project's retention invoice line description. If you do not use retention for this project, leave this field blank.
When you are ready to bill the retained amount as an event, clear this field.
Enter the percentage amount that you want to retain from invoices. If you do not use retention for this project, leave this field blank.
When you are ready to bill the retained amount as an event, clear this field.
Using Effective Dates to Enable and Disable Options