The % Open Current is the percentage of the ordered quantity not yet received, but within the receipt tolerance days or not past due.
The % Open Past Due is the percentage of the ordered quantity not received by the promise date and beyond the receipt tolerance days.
The % Received On Time is the percentage of the ordered quantity received on the promise date or within the receipt tolerance days.
The % Received Late is the percentage of the ordered quantity received after the promise date and outside the receipt tolerance days.
The % Received Early is the percentage of the ordered quantity received before the promise date and outside the receipt tolerance days.
The Days Variance is calculated as the summation of the date differential (transaction date subtracted from promise date) multiplied by the corrected received quantity (the received quantity plus or minus corrections) for each shipment, all divided by the total corrected received quantity. The result is the quantity per day the supplier is in variance.