Project and Task PSI Columns

The default Project and Task folders use 27 columns (three text and 24 numeric).

Order Column Prompt Column Description / Formula Description Type
1 Project or Task Project Number or Task Number Text
2 Project Name or Task Name Project Name or Task Name Text
3 Ovr Bgt Over Budget:
Displays an asterisk (*) if the ITD actual burdened cost is greater than 110% of the ITD burdened cost budget amount; if not over budget, column is blank.
Text
4 ITD - Rev Bgt ITD (Inception-to-date) revenue budget amount Number
5 ITD - Act Rev ITD actual revenue Number
6 ITD - Cst Bgt ITD current burdened cost budget amount Number
7 ITD - Act Cost ITD actual burdened cost Number
8 Commit Amt PTD (Period-to-date) commitment burdened cost Number
9 PTD - Cst Bgt PTD current burdened cost budget amount Number
10 PTD - Act Cost PTD actual burdened cost Number
11 ITD - Bgt Hrs ITD current labor hours budget amount Number
12 ITD - Act Hrs ITD actual labor hours Number
13 PTD - Bgt Hrs PTD current labor hours budget amount Number
14 PTD - Act Hrs PTD actual labor hours Number
15 Tot - Rev Bgt Total current revenue budget amount Number
16 Tot - Cst Bgt Total current burdened cost budget amount Number
17 Tot - Bgt Hrs Total current labor hours budget amount Number
18 Tot - Orig Rev Bgt Total original revenue budget amount Number
19 Tot - Orig Cst Bgt Total original burdened cost budget amount Number
20 Tot - Orig Bgt Hrs Total original labor hours budget amount Number
21 ITD - Orig Rev Bgt ITD original revenue budget amount Number
22 Fin % Cmplt Financial percentage complete:
ITD actual burdened cost / total current burdened cost budget amountX100
Number
23 Hrs % Cmplt Hours percentage complete:
ITD actual labor hours / (Total current budget labor hoursX100)
Number
24 Est to Cmplt Estimate to Complete:
Total current burdened cost budget amount - (ITD actual burdened cost + PTD commitment burdened cost)
Number
25 Tot Cst - ITD ITD total cost:
ITD actual burdened cost + PTD commitment cost
Number
26 Bgt Mgn Budgeted margin:
Total current revenue - Total current burdened cost
Number
27 Act Mgn - ITD ITD Actual margin:
ITD actual revenue - ITD actual burdened cost
Number