Update Project Summary Amounts

This process updates the project summary amounts with new cost, commitment, and revenue transactions and any new baselined budget versions.

You can run this process as many times as you want.

Process Submission

From the Submit Request window, submit one of the PRC: Update Project Summary Amounts processes:

See: Submitting Requests

Process Parameters

Accumulate Cost. Enter Y if you want the Update Project Summary Amounts process to summarize cost amounts.

Accumulate Revenue. Enter Y if you want the Update Project Summary Amounts process to summarize revenue amounts.

Accumulate Budgets. Enter Y if you want the Update Project Summary Amounts process to summarize budget amounts.

Accumulate Commitments. Enter Y if you want the Update Project Summary Amounts process to summarize commitment amounts.

From Project Number. Enter the number of the project that you want the Update Project Summary Amounts process to use as the low end of the project number range within which it selects projects to process. If you leave this parameter blank, the process selects all eligible projects whose project numbers come before the project number entered in the End Project Number process parameter.

Note: You do not need to enter a valid project number in the From/To Project Number fields. This allows you to enter a range that will limit the process to the projects you want to summarize without knowing the actual lowest and highest project numbers that will be selected. See: No List of Values for Project Number Range Parameter.

To Project Number. Enter the number of the project that you want the Update Project Summary Amounts process to use as the high end of the project number range within which it selects projects to process. If you leave this parameter blank, the process selects all eligible projects whose project numbers come after the project number entered in the Start Project Number process parameter.

Project Number. Enter the name of the project for which you want to submit the Update Project Summary Amounts for a Single Project process.

Budget Type. Select the budget type that you want the Update Project Summary Amounts process to use.

Expenditure Type Class. If you are running the Update Project Summary Amounts process for one project, you can optionally select one expenditure type class that the Update Project Summary Amounts process will use.

Resource List Name. If you are running the Update Project Summary Amounts After a Resource List Change process, you can optionally select one resource list that the Update Project Summary Amounts process will use.

Output Reports

Two output reports show you the results of this process: