Updating Project Summary Amounts
You run the Update Project Summary Amounts process to update the project summary amounts with new cost, commitment, and revenue transactions and any new baselined budget versions. You can run this process as many times as you want.
If you maintain to-date amounts by GL period, select the PA period in the PA Periods window that is the first PA period of the GL period that you are selecting as the current reporting period.
You run the Update Project Summary Amounts After a Resource List Change process when you have changed the resource list and want to map historical transactions to resources using the new resource list.
Prerequisites
Enter expenditure items and distribute costs (optional).
Accrue and release revenue (optional).
Create new commitments (optional).
Create a new current budget (optional).
Set the current reporting period.
To update project summary amounts:
1. Navigate to the Submit Request window.
2. Choose the PRC: Update Project Summary Amounts process or the PRC:Update Project Summary Amounts After a Resource Change process.
3. Enter the project range or project number for which you want to update summary amounts. You may choose to submit this process many times for different project ranges.
4. Optionally, enter other options to control what Oracle Projects updates.
To update project summary amounts after changing a resource list:
1. Choose PRC: Update Project Summary Amounts After a Resource List Change process in the Submit Request window.
2. Enter the From/To Project Number and Resource List Name. You may choose to submit this process many times for different project ranges.
See Also
Update Project Summary Amounts
Summarizing Actuals and Commitments by Resource
Setting the Current Reporting Period