Comparing Budget to Actual and Commitment Amounts
You can review current and original budgeted amounts and compare them to actuals and commitment amounts.
You review the budgeted amounts for one cost budget type and one revenue budget type at a time.
The default cost budget type is the predefined Approved Cost Budget. The default revenue budget type is the predefined Approved Revenue Budget.
Prerequisite
To review a different cost or revenue budget type:
- Choose Revenue Budget Type from the Special Menu.
You can choose a different cost or revenue budget type from all budget types from the Project Status window. If you choose a budget type from the Task Status window, you can only select from the budget types assigned to the project.
See Also
Overview of Project Budgets
Define Budget Types